Trial runs have commenced on the 19-km Phase 2A section of Bengaluru Metro’s Blue Line along the Outer Ring Road, with passenger services targeted to begin by mid-2027. The testing began from KR Puram on November 24, covering the first four stations towards Mahadevapura, and will be progressively extended to the remaining stations in the coming weeks.
Karnataka Greater Bengaluru Development Minister Krishna Byre Gowda inspected the ongoing trials at Doddanekkundi Metro Station and said the corridor would provide a long-term public transport alternative along one of Bengaluru’s busiest employment and mobility stretches. An estimated 11-12 lakh people work along the Outer Ring Road corridor, which connects several major technology and commercial hubs.
The Phase 2A section extends between KR Puram and Central Silk Board and comprises 13 stations. Trial operations will continue through November, with testing expected to cover another four stations in December. The next major requirement is the installation of the automatic signalling system, which the government expects to complete by January 2027. Mandatory safety certification is scheduled to begin after February, followed by further testing and approvals. The overall testing and certification process is expected to take another seven to eight months.
The 19-km stretch forms part of the 58.2-km Blue Line, which will connect Central Silk Board with Kempegowda International Airport through KR Puram and Hebbal. The entire corridor is being developed at an estimated cost of ₹20,000 crore. While Phase 2A is targeted for passenger operations by mid-2027, the government is also working to accelerate construction on Phase 2B, particularly along the KR Puram-Hebbal section.
Gowda said officials had been directed to coordinate closely with contractors and expedite pending works on the airport corridor. The state government is targeting completion of the entire Blue Line within the next 18 months.
The minister also highlighted the financial challenges associated with Metro expansion, including increased loan repayment obligations due to foreign exchange fluctuations. The state government is making budgetary provisions and releasing funds as required to prevent funding constraints from delaying ongoing projects.
Bangalore Metro Rail Corporation Limited (BMRCL) currently faces an annual loss of approximately ₹600-700 crore, including depreciation, although it is estimated to record an operating surplus of ₹50-60 crore when depreciation is excluded. The commencement of Blue Line services is expected to increase operating expenditure. However, the state government has clarified that no decision has been taken to increase Metro fares.